Purpose:
The Ministry of Transport and Road Development presented a progress report on the ongoing construction of the Burao-Berbera highway. The statement included updates on project phases, funding status, and expected completion dates
Description:
The statement from the Ministry covered the following key points:
Project Scope: Construction of a 172 km highway connecting Berbera to Burao, expected to improve trade and regional integration.
Funding: Project co-funded by the Somaliland Government and international partners, including the Abu Dhabi Fund.
Progress:
65% of the road foundation completed.
40 km of asphalt already laid.
Drainage systems installed in flood-prone areas.
Challenges:
Delays due to heavy rains in February 2025.
Material supply issues affecting progress in Sahil region.
Expected Completion: Full completion expected by December 2025.
Community Impact:
Over 500 local workers employed.
Easier access to Berbera Port and regional markets anticipated.
Next Phase: Focus shifting to final paving and safety signage installation.